Electrical Preventative Maintenance

Electrical Preventative Maintenance

pdf icon Electrical Preventative Maintenance (EPM)

According to the Institute of Electrical and Electronics Engineers (IEEE), the failure rate of electrical components is three times higher for systems where preventative maintenance is not performed.

As electrical loads cycle between high and low demand, thermal expansion and contraction cause connections to loosen. Without cleaning, electrical panels accumulate dust, creating a high resistance path on those loose connections, leading to more than 30 percent of electrical failures.

Another 17 percent of electrical failures are attributed to live electrical components being exposed to moisture.

The fundamental concept of EPM is to keep it cool, clean, dry, and tight. It is cheaper to repair equipment before it fails.

Causes of Electrical Distribution System Failures*

  • Loose connection/part 30.3 percent
  • Moisture 17.4 percent
  • Line disturbance (other than lightning) 10.4 percent
  • Defective/inadequate insulation 9.9 percent
  • Lightning 8.1 percent
  • Foreign objects/short circuiting 7.3 percent
  • Collision 3.9 percent
  • Overloading/inadequate capacity 2.4 percent
  • Accumulation of dust, dirt and oil 2.2 percent
  • All other causes 8.1 percent

Preventing electrical failure

1. Hire qualified personnel.

Make sure the people who perform the EPM program are trained to work on the specific equipment being maintained or tested. Special training is required for high-voltage equipment and protective relay devices.

2. Schedule regular inspection, testing, and servicing of equipment.

While the time period between maintenance depends on environmental conditions, EPM should be performed at least once every three years and more often for critical components.

A thermographic inspection of all electrical equipment should be completed prior to the scheduled EPM outage. This survey is a non-invasive method that indicates potential problem areas such as loose or dirty connections, load imbalances, or improper installation of equipment. It helps determine the resources you will need during your scheduled outage to perform EPM.

Ideally, a thermographic inspection should be done during peak-load conditions by a certified, experienced thermographer.

Plans should be made to have all circuit breakers and disconnect switches repeatedly opened and closed during the shut-down period to ensure proper operation. In addition, protective relays and circuit breaker trip devices need to be tested and calibrated on a regular basis.

Oil-filled transformers, circuit breakers, and disconnect switches should have samples of the insulating oil screen-tested as a means of identifying potential problems with those components.

Transformer oil should also undergo dissolved gas analysis to identify specific adverse conditions present inside the unit. Equipment insulated with SF6 gas should be inspected and leak-tested to ensure the integrity of the gas system.

3. Use sound judgment in evaluating results.

Make sure the person reviewing the test reports has a thorough understanding of the specific subject matter so responsible decisions can be made.

4. Perform the necessary work.

Preliminary testing and inspection help to focus your resources on the critical tasks, but ultimately you need to have scheduled outage to perform the necessary work.

5. Keep concise and complete records.

A clear record-keeping system will help keep the EPM program cost-effective by ensuring that work is done when on time. Tracking of test results over time can identify a potential failure that can be corrected before it happens.

 

Download "Electrical Preventative Maintenance" Read more loss control materials Learn about our business insurance coverages

 

 

*Based on Hartford Steam Boiler claims data

 

 

This bulletin has been prepared as an underwriting reference for members of Grinnell Mutual Reinsurance Company and does not signify approval or disapproval by the Company of any product or device. Please do not copy or reproduce any portion of this bulletin without the written permission of Grinnell Mutual Reinsurance Company. The information included in this publication and program was obtained from sources believed to be reliable, however Grinnell Mutual makes no guarantee of results and assumes no liability in connection with its use. It is the user’s responsibility to comply with any applicable regulations or laws. Information obtained from or via Grinnell Mutual should not be used as the basis for legal advice, but should be confirmed with alternative sources.